Construction Schedule by Month
May 2010
Install floor beam, sill plate, rim joist, & floor joists
Install floor sheathing, set exterior & interior walls
Brace walls, wrap house
Mark roof truss locations, set & brace trusses
Sheath roof; move shingles to roof
Shingle house & garage
Install windows & doors; finish shingling
June 2010
Install siding; drywall garage
Work on siding; install garage door
Finish siding; insulate walls; install vapor barrier
Finish insulating walls; install soffits
Work on soffits; sheetrock ceilings
Finish soffits; sheetrock walls
Sheetrock walls; blow in insulation
July 2010
Sheetrock walls; blow in insulation
Finish Sheetrock
Paint interior
Install kitchen cabinets
Install interior doors
Finish door installation
Install base board and closet shelves
August 2010
Finish base boards and door trim
Install misc bathroom fixtures and appliances
Finish odds and ends
Clean up and home owner walk thru